Our approach was considered and organised. We pre-purchased and locked in prices on materials to avoid inflation where we could and worked closely with the builder to adapt to the ever-changing programme. We stayed loyal to the builder through the hard times, got the job over the line, and have continued winning work with them on the back of it, having built a strong relationship across the life of the project.
The Brief
Halcyon was quoted during COVID and hit by significant supply chain issues, large-scale material and labour inflation, and major programme delays with site closures and re-openings. It tested the developer and builder throughout.
Our Approach
The Results
The job was completed and, just as importantly, we maintained a strong relationship with the builder through a genuinely difficult period in the industry.